No call from our Site Supervisor today, and the only reason I can think that that would be the case, is that we have our “Pre-lining Inspection” with him on Tuesday morning (Labour Day long weekend here in NSW), so he is probably just waiting for that.

We also, coincidentally, have our Private Certifier Inspection booked in for the same morning, however just earlier than ours – so Houspect will also be doing their rounds on Tuesday morning.

Our take on the week that was, is that Alarm & TV rough-in happened early in the week. Electrical rough-in came next, although they were on different days. The two small Colourbond roofs were finalised, and Insulation batts were delivered. The Scyon Wall Panelling (weatherboard) at the rear of our home was also completed.

Brick Clean did not happen, and the Scaffolding is definitely still there.

Looking forward to Tuesday!

 

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s